Hi All,
We are upgrading from SRM4.0 to SRM7.0 SP07 in classic scenario. We switched to Process Controlled Workflow.
We have a CUSTOM application where the requisition items are entered and a Shopping Cart is created in SRM through Function Module BBP_PD_SC_CREATE. When the Shopping Cart is created in SRM , the Process Controlled Worflow is triggered successfully.
In the custom application , we allow users to do changes to the requisition that are awaiting approval.The changes are updated in SRM Shopping Cart through function module BBP_PD_SC_UPDATE. It is noticed that the workflow process levels are not re-started after the shopping cart is updated through FM BBP_PD_SC_UPDATE.
However , the process levels are re-started when the change is directly done to the Shopping Cart in SRM POWL. We want the process levels to be re-started even when the changes are done through BBP_PD_SC_UPDATE. The users are used do changes to the requisition through the custom application. We also noticed that system does not go through BAdI /SAPSRM/BD_WF_PROCESS_RESTART when changes are done to the SC through BBP_PD_SC_UPDATE.
Is there any way that we can trigger process level re-start when SC is changed through FM BBP_PD_SC_UPDATE
Thanks
Sukumar